Waste & Environmental Cleanup
Featured Environmental Story
CNN interviews residents of Shell Bluff, GA about the lack of monitoring in their community which hosts a nuclear power station and is across the Savannah River from a radioactive superfund site.

Cleanup Sites
Click here to view the Department of Energy's list of Environmental Management sites by state
Print  


 


Past and Present

The Department of Energy (DOE) has produced radioactive materials for nuclear bombs; designed, built, and tested nuclear weapons; and developed reactor and other technologies with little concern for the environmental harm those activities cause. The inevitable result is that all DOE sites are polluted. Nevertheless, DOE remains far more interested in protecting its pollution-causing activities than in correcting the harm they have already done.



DOE is not meeting its legal and ethical responsibility to clean up the legacy of more than 60 years of radioactive and toxic contamination. Instead, DOE is promoting nuclear activities that will create additional pollution and threaten the health of future generations. Currently, water near some DOE facilities, such as Paducah, KY, and Pantex, TX, remains unfit to drink. Some of the nation’s major water sources, including the Columbia River, Snake River Aquifer, and Ogallala Aquifer, are threatened.


After declaring the Yucca Mountain project dead, the Obama Administration called for a "Blue Ribbon Commission on America's Nuclear Future" to determine what should be done with US high level nuclear waste. The Blue Ribbon Commission has issued its draft report. A final report will be issued in January


LANL Sets Cleanup Goal 17,000 Drums Of Waste To Be Moved
published Monday, January 09, 2012  638 Views :: 0 Comments

The following article on Los Alamos National Laboratory's ever-changing cleanup schedule quotes ANA Director Susan Gordon and ANA member Scott Kovac giving their perspectives on Los Alamos' remediation plans.

January 6, 2012

By Mark Oswald and John Fleck
From the Albuquerque Journal

POJOAQUE — Los Alamos National Laboratory on Thursday committed to moving the equivalent of 17,000 drums of radioactive waste that have been stored above ground for decades off lab property by 2014.

But lab officials also said they can’t meet their commitment to clean up other lab hazardous waste by 2015.

Moving the waste drums — which caused consternation and gained international press attention during last summer’s Las Conchas Fire as flames headed toward Los Alamos — is a top state priority.

But the longer-term cleanup goal, established in a 2005 agreement known as a “consent order,” has been suspect for some time because of a shortfall in federal money for lab cleanup work.

“They have historically been underfunded for this work,” Jim Davis, director of the New Mexico Environment Department’s Resource Protection Division, said in an interview Thursday.

Congress this year provided $189 million for cleanup at Los Alamos, $169 million less than the Obama administration said it needed to stay on schedule to meet cleanup milestones.

“It’s not possible for DOE to meet the 2015 consent order,” George Rael, the Department of Energy’s assistant manager of environmental projects at Los Alamos, said at a public meeting Thursday night. He said he hoped the state would agree to reevaluate the 2005 deal setting 2015 clean-up deadlines.

But Davis said the state won’t consider renegotiating the consent order on broader clean-up work until it sees progress on getting the 3,706 cubic meters of above-ground waste off part of the lab known as Area G.

The state wants “to see a trend” that the drums are going away as promised before it considers renegotiating the 2005 deal, Davis said.

Lab and state officials used a meeting before the Northern New Mexico Citizens Advisory Board in Pojoaque to roll out changes in the lab’s cleanup approach, which are being driven in part by changes in state priorities and in part by the lab’s struggle to respond to funding shortfalls.

The lab’s commitment to remove the radioactive waste stored above ground by 2014 meets a request made by Gov. Susana Martinez, who made removal of the waste a top priority after the Las Conchas fire burned to within 3½ miles of Area G. The waste has been kept there in drums and other containers stacked in temporary structures above ground.

M. Lee Bishop, the federal manager for transuranic waste at Los Alamos, noted that the above-ground waste “caused a tremendous amount of public concern” during the big fire.

He said the feds agree with the state environmental regulators that moving the waste to the Waste Isolation Pilot Plant in Carlsbad is the now lab’s highest clean-up priority.

It’s estimated it will take 585 truck shipments to get the material to WIPP, said Dan Cox, the lab’s deputy associate director for environmental programs. The lab has stepped up removal of the drums in recent years, with more than 450 shipments to WIPP since 2009.

Representatives of a couple of lab watchdog groups urged the state to not give up on the consent order for broader lab clean-up work.

The order is “the stick, and without it they won’t do anything,” said Susan Gordon, director of the Alliance for Nuclear Accountability.

Scott Kovac of Nuclear Watch New Mexico said the state shouldn’t let up on requiring clean-up of other parts of the lab. “We don’t want the lab to be a permanent waste site,” he said.

State Environment Secretary David Martin said the new agreement between the state and the feds to get the aboveground waste off-site by the end of 2014 is not a legal document but is an understanding on “how to move forward with new priorities.”

The 2005 consent order between the state and the lab laid out cleanup milestones had included a 2015 deadline for remediating Area G.

At the time the deal was made, both the state and the lab viewed the agreement, which sets legally binding milestones, as a way to pressure the federal government into providing the money needed to clean up environmental messes at Los Alamos. But getting money for the work has become increasingly difficult.

State officials said lab and federal officials began raising the possibility of renegotiating the consent order a year ago, but that the state has thus far resisted.

“The state is not willing to renegotiate the consent order right now,” New Mexico Environment Department general counsel Ryan Flynn said in an interview Thursday.

State officials say they’re concerned that any indication of a willingness to let deadlines slip would make it easier for Congress to cut funding for lab cleanup work.



Resources

Public Comments


ANA's statement to the Blue Ribbon Commission at their Denver meeting in September 2011


ANA's comment on the April 2011 Department of Energy Greater than Class C Waste Draft Environmental Impact Statement.


FACT SHEETS

2011 ANA fact sheet on Nuclear reactors and Waste


Greater Than Class C Waste Fact Sheet from the Snake River Alliance


Department of Energy
Environmental Cleanup:�
Underfunded and Inadequate  2007


Yucca Mountain:
Not the Solution to Nuclear Waste
  2007


Spent Fuel Reprocessing and the Global Nuclear Energy Partnership


ANA Water Report: 


DANGER LURKS BELOW
The Threat to Major Water Supplies from US Department of Energy Nuclear Weapons Plants


GTCC Resources
The Department of Energy is seeking comments to determine the scope of the planned Environmental Impact Statement dealing with the "Disposal of Greater-Than-Class-C (GTCC) Low-Level Radioactive Waste." 

Watch this space and this page for resources helpful in composing your own comments.