August 4, 2011
By Annette Cary
Tri-City Herald
RICHLAND -- After 10 and a half years, the $12.2 billion Hanford
vitrification plant is 60 percent complete, by the calculations of
Department of Energy contractor Bechtel National.
The milestone includes engineering, procurement, construction and start-up and commissioning-related activities.
“Woohoo!” was the reaction of the regulator for the project, the
Washington State Department of Ecology, as summed up by Dan McDonald,
the project manager for Hanford waste treatment.
“We’re very pleased with the progress,” he said.
Hitting
the 60-percent mark positions work to continue the transition from the
design and build phase of the massive project to the commissioning and
operating phase, he said.
“Ecology looks forward to the continued rate of progress, completion of activities and starting up,” he said.
The
plant is being built to turn much of the 56 million gallons of
radioactive waste held in Hanford’s underground tanks into a stable
glass form for disposal. The waste is left from the past chemical
processing of irradiated fuel to produce plutonium for the nation’s
nuclear weapons program.
“More
than 16,000 workers have contributed to this project to date,” said
Frank Russo, Bechtel National project director, in a congratulatory memo
to employees.
Since
construction began in 2001, 213,000 cubic yards of concrete, 18,000 tons
of steel and more than 100 miles of piping and conduit have been
installed, he said.
Engineering
on the vitrification plant is nearly 85 percent complete and workers
have completed 58 percent of the procurement work required to supply all
permanent plant material and equipment.
“This
excellent performance reflects your continuing emphasis on delivering
quality work in a safe manner while meeting cost and schedule
objectives,” he told workers.
The
project hit the halfway point in fall 2009, according to DOE. That
marked significant progress after three earlier plans to build a tank
waste treatment plant had been terminated, according to Washington state
documents.
“We
appreciate the diligence and dedication of our work force bringing us
one step closer to operations in 2019,” said Dale Knutson, DOE federal
project director for the plant.
The
latest accomplishment at the plant was issuing the final design for the
concrete walls of the Pretreatment Facility, the largest building at the
plant.
When
complete, the Pretreatment Facility will include 113,000 cubic yards of
concrete. It’s being built in six concrete wall elevations, with each
elevation as large as 28 feet tall, 460 feet long and four feet thick.
The concrete walls will be 109 feet high with steel columns and roof
trusses that extend beyond the walls to an overall height of 120 feet,
with emission stacks reaching nearly 200 feet high.
The
extensive wall design is supported by more than 15,000 pages of
calculations and 500 drawings. More than 500 engineers worked on the
building’s wall design over several years.
“These
are no ordinary walls; they are designed to nuclear-quality standards
and must meet strict regulations and requirements that will ensure the
integrity and safety of the facility and its equipment,” Russo said in a
statement. “Literally, each inch of wall is reviewed and checked
multiple times by multiple people.”
Each
wall in the Pretreatment Facility includes a complex rebar grid, or
“curtain,” that reinforces the strength of the surrounding concrete.
Many of the walls also have embedded steel plates that will be used to
connect materials and equipment requiring precise placement.